(Published in Part – III Section 4 of the Gazette of India, Extraordinary)
| No. 77 | New Delhi, the 31st May, 2000 |
Tariff
Authority for Major Ports
Notification
No.TAMP/62/99-MBPT - In exercise of the powers conferred by Section 48 of the Major Port Trusts Act, 1963 (38 of 1963), the Tariff Authority for Major Ports hereby approves the proposal of Mumbai Port Trust relating to rationalisation of Section I to III and V of the Dock Scale of Rates, as in the Order appended hereto.
SCHEDULE
Case No. TAMP/62/99 -
MBPT
The Mumbai Port Trust (MBPT)
Applicant
O R D E R
(Passed on this 12th day of May 2000)
This
relates to a proposal forwarded by the Mumbai Port Trust (MBPT) about rationalisation of
rates under Section I to III and V of its Dock Scale of Rates (DSR).
2.
The MBPT has
stated that the wharfage charges leviable at the Docks were last revised in 1991 and based
on the cost figures for 1997-98, the Service General cargo handled at the Dock,
for which wharfage on cargo is recovered, is indicating a 2% deficit. However, the MBPT has pointed out that its
proposal is not to revise the existing wharfage charges but to simplify / rationalise the
tariff further. The salient points of the
proposal are given below:
(i). In 1991, the
schedule of wharfage charges was modified and 14 rates were prescribed consisting of
eleven rates on weight basis, one rate on unit basis and two rates on ad valorem basis.
Certain types of cargo which are not bulk in nature have to be assessed to wharfage
charges on volume basis just because the wharfage schedule indicates a rate for such cargo
on volume basis. To avoid such situation and
to simplify the wharfage schedule further, the MBPT has proposed to regroup the
commodities and prescribe only ten rates in the wharfage schedule with one rate on unit
basis, seven rates on volume (weight) basis and two rates on ad valorem basis.
(ii). The wharfage charges
on POL and POL products handled at the Marine Oil Terminal (MOT) were revised in 1996. The MBPT has now proposed to incorporate these
charges in the wharfage schedule of Docks Scale of Rates (DSR) so that same rates can be
applied for POL handled at the docks.
(iii). The MBPT has proposed to
reintroduce a rebate of 20% in wharfage charges on coastal cargo which was withdrawn in
1985.
(iv). In 1982, wharfage on
imported cargo allowed to store in the boned warehouses by the Customs was fixed as
Rs.25.00 per tonne. In 1991, this rate was
revised to Rs.37.50 per tonne. However, this
rate has not been included in the DSR. The
MBPT has proposed to round off the rate to Rs.38 per tonne, and include in the DSR.
(v). A separate wharfage
rate on weight basis for ship-to-ship transhipped cargo and cargo transhipped or received
for transhipment by road was introduced by the MBPT in 1988. The rate for such cargo was revised in 1991 as
Rs.90/- PMT and Rs.37.50 PMT respectively; but, again, not incorporated in the DSR. It has
been proposed to prescribe a separate wharfage rate for such levy and to round off the
rate of Rs.37.50 PMT to Rs.38/- PMT.
(vi). Citing the slower rate of
clearance of cargo as one of the reasons for congestion in the Port, the MBPT has proposed
to raise the existing minimum rate of demurrage by 20% (Rs.30/- per tonne per day) and
alter the time-frame for the charges from the existing 30 days to 20 days and 60 days to
40 days respectively as approved by the MBPT Board in 1996.
(vii). In case of cargo vessel and barges
sinking or grounding along with the cargo, certain additional formalities are required to
be finalised before the consignees are able to effect clearance. It has, therefore, been
proposed to give additional 7 free days in such cases in order to encourage speedy
clearance of the cargoes. Section II of the
DSR has been proposed to be suitably modified.
(viii). It is proposed to delete Clause 7 of
Section IIA of the DSR relating to goods shown as excess in the outturn of the vessel as
the provision has been seen to lead to unnecessary litigations in the past.
(ix). It is proposed to delete the
existing Clause 8 of Section II of DSR relating to Demurrage on goods detained by Customs
for special examination involving analytical or technical test other than the ordinary
process. The port has felt it necessary to assess the pros and cons of each case
separately and consider remission on merits depending on the time taken by statutory
authorities other than Customs. The port has proposed that all cases of such detention are
to be placed before its Board for consideration of remission under Section 53 of the MPT
Act.
(x). It is proposed to
amend the existing provision in Section II B to prescribe a uniform free period of 7 days
irrespective of place of storage of the export cargo. It is also proposed to provide
pre-shipment storage facilities for aggregation of export cargo for carrying out Customs
examination and preparing pallets and unit load. In
order to encourage exports a suitable provision on demurrage free days of 30
days from the date of receipt at the area earmarked for this purpose, is also proposed to
be incorporated in the DSR.
(xi). Presently goods sold in
auction are levied demurrage at the rate of Rs.70 per tonne per day, if they remained
uncleared beyond the free period. This rate
is in effect from 1979 onwards. It has been proposed to revise the rate to Rs.100 per
tonne per day or part thereof.
(xii). It is proposed to define
over-dimensional packages in the Scale of Rates which will be eligible for benefit under
Sub Section A of Section III of the DSR in order to extend the benefit only in cases where
clearance is delayed due to non-availability of special types of transport or for want of
special permission from the concerned authorities.
(xiii). On transhipment cargo, inside
transhipment containers, a consolidated wharfage is levied. This payment is made by Vessel
Agents who recover freight in US $. It has,
therefore, been proposed to prescribe the wharfage on cargo inside transhipment containers
in US $.
(xiv). It is proposed to prescribe licence fee
to the ICD containers removed by the road at par with ICD containers by rail. The port has proposed to incorporate suitable
provisions in the DSR (a) for recovery of charges in respect of import loaded containers
discharged at other Indian Ports and brought to Mumbai by rail or road for effecting
clearance of cargo; (b) in respect of containers stuffed at the Mumbai Port premises and
removed for shipment from a port other than the Mumbai Port; and, (C) containers received
at Mumbai Port other than the Mumbai Port premises and removed for shipment through Ports
other than Mumbai.
(xv). In order to encourage speedy
clearance of FCL, it is proposed to levy a uniform wharfage charge per TEU, irrespective
of the nature of cargo, if a loaded container is removed from the port premises within 7
days following the GLD the vessels.
(xvi). The port has proposed to incorporate a
provision in the DSR under Section (v) granting exemption of Licence (Storage) Fees on the
Customs detained containers stored in the area allotted to the Customs on rental
basis.
3.
The
proposal of the MBPT was circulated to the user agencies.
The comments received from them are summarised below:
(i). Container
Shipping Lines Association (CSLA)
We have no
comments to offer. However, we wish to
forward a copy of the comments received from M/s. Relay Shipping Agency Limited requesting
that a separate tariff for domestic container handling charges may be included in all
major ports tariffs. The TAMP must take
the initiative to force Port Trusts to take steps in this regard.
(ii). Indian National
Shipowners Association( INSA)
(a). As per Clause 9 of DSR, MBPT allows 80% remission in
demurrage for goods detained by Customs. Likewise,
the ground rent on containers, containing such goods, must also be remitted for the same
reasons.
(b). As per Clause 15, containers detained by any wing of
Customs will not be shifted to Up Departure yard. The
Shipowners position is that storage charges on such containers shall cease to occur from
the day of Customs notice of detention. Secondly, such containers shall be de-stuffed
within 7 days and empties returned to the carrier without charging any storage charges.
(c). The ship-owner is helpless in such a case and is being
unduly burdened with the storage charge on containers and he is debarred from utilising
his equipment for no fault of his own.
(d). The process of auctioning over stayed / abandoned goods
beyond 60 days shall be expedited and disposed off at the most in three auctions. Shipping line shall not be held responsible for
cargoes lying in ports beyond 60 days for which the carrier has requested the port for
disposal. The shipping line shall not be
charged for delays beyond 60 days. The sale
proceeds of such goods are to be shared between the port and the Customs on a 50:50 basis.
This being so, the Shipping Line shall not be charged any ground rent. These have already been decided in the Export
Promotion Board meeting held on 20.03.1999 under the chairmanship of the Cabinet
Secretary.
(e). For cargoes / containers coming from abroad, the MBPT
shall merely prescribe a consolidated transhipment fee, because calculating ground rent on
per day basis makes matter difficult to quote and charge a fee as a part of freight long
before the event. Port shall not charge any
wharfage on cargo in the containers, as the cargo is not being handled; it is mainly
transiting to an ICD. Ground rent on a
container waiting for movement to an ICD by rail shall be stopped the day the indent is
registered and container is made available to MBPT for railing. This charge shall be a lump sum fixed / worked out
on reasonable actual basis as per ports transparent experience.
(f). A separate and concessional charge may be provided for
coastal / domestic containers.
(iii). Shipping Corporation
of India (SCI)
The comments of
the INSA (as give above) are repeated and reiterated.
4.
The
comments received from the above users were sent to MBPT for their information / comments.
In it reply, the MBPT has given following further observations:
(i). As regards the
provision for concessional rate for domestic container and coastal cargo/container, a
rebate of 20% in wharfage charges in respect of cargo of Indian Origin imported from or
exported to the ports within the limits of Union of India has been proposed in the
amendment. However, it is agreed that concession to coastal cargo is necessary. A separate proposal in this regard will be
considered by the Board of MBPT.
(ii). As regards grant of
80% of remission in licence fees in respect of containers containing goods detained by
Customs, it has been the policy of MBPT not to grant remission except on demurrage on
cargo; and, therefore, the proposal for remission in ground rent on container is not
acceptable. In order to minimise ground rent
charges in such cases, a provision has been proposed that the container with the cargo
detained by Customs need to be shifted to the area earmarked for storage of such
containers.
(iii). As far as the demand for
de-stuffing of containers detained by Customs within seven days and also cessation of levy
of storage charges from the day of notice by the Customs, the MBPT cannot give any
unilateral assurance since it involves the Customs also.
(iv). The suggestion for
expeditious auction of overstayed/abandoned goods beyond 60 days, at the most, in three
auctions has already been implemented. However, this need not be a part of the DSR, being
a procedural matter.
(v). The stipulation that
Shipping line should not be held responsible or charged for cargoes lying in ports beyond
60 days for which carrier has requested the port for disposal cannot be made. However, if
the Bills of Landing are duly discharged by the vessel agent/line and delivered to the
consignees, they are not held responsible. This also need not be a part of DSR as it is a
procedural mater and is already in force.
(vi). The proposal that sale
proceeds of over stayed/abandoned goods be shared between the port and the Customs on a
50:50 basis, and that shipping lines shall not be charged any ground rent is not a
relevant one to be a part of the Scale of Rates. Allocation of sale proceeds is covered
under Section 63 of the Major Port Trusts Act and any change can be effected only with
amendment to the Act.
(vii). A composite box charge on ICD
containers was levied earlier.
(viii). The agreement about non-levy of wharfage
charges on cargo inside the transhipment containers is not acceptable for the following
reasons:
(a). Since the containers are loaded with cargo, port has to
provide security and watch & ward facilities to these containers.
(b). Though the cargo is not handled directly, cargo along with
the container is handled by the port at the hook point.
(c). Loaded transhipment containers occupy ports storage
area. However, no demurrage is levied on cargo inside the transhipment containers.
5.
Subsequently,
the MBPT has forwarded another proposal to amend the earlier (proposed) provision in
Section II B-Exports-item (3) on cargoes stored in the areas nominated by the Board for
aggregation of export cargo. Since the
provision vesting powers in the Board to nominate the area is not practical and such
arrangements are to be done by the Traffic Department depending on operational
requirements, the port has proposed that the words by the Board in the said
provision may be deleted.
6.
A
joint hearing in this case was held in Mumbai on 6 March 2000. During the joint hearing, the Mumbai Port Trust
made some written submissions, highlighting the salient features of its proposals and
giving a summary of its comments on the views expressed by the port-users. They have added that as per the cost statements
for 1997-98 and 1998-99, the activity of General cargo handled at the Docks indicates a 2%
and 11% deficit respectively.
7.
During
the joint hearing, the following submissions were made by different participants:
Mumbai Port Trust
(i). There is no
increase of wharfage. The proposal only
suggests rationalisation. The proposal of
increase of 20% in Demurrage is based on a Committees report. The Committee included
representation of Port Users also.
(ii). The port has suggested
a 20% rebate for coastal cargo.
(iii). In order to boost exports,
30 days free storage time is given.
(iv). In the case of detention by
the Customs, there will be no charge for storage in the allocated area. It is for the users to shift the goods to the
allocated area.
The Bombay Custom House Agents
Association (BCHAA)
(i). There is no case
for any increase.
(ii). On ad valorem rates of
wharfage, the port has earned a lot between 1991 to 1999 on account of depreciation of the
rupee. Similarly, the port has earned a lot
on account of vessel-related charges denominated in dollar terms.
(iii). Wharfage on imported cargo,
allowed to store in bonded warehouses, is being raised from Rs.25/- to Rs.38/- and the
case is not simple rounding off. The earlier
increase from Rs.25/- to Rs.37.50 was not approved by the Government.
(iv). The existing provision
regarding goods shown as excess in the Out Turn Report should not be withdrawn. Why should
trade pay more for somebody elses error? Additional
entry must be granted.
(v). Withdrawal of
concession on demurrage on goods detained by the Customs amounts to increase of rates.
(vi). Demurrage free days of 30
days for export cargo stored in earmarked area is good.
But, the free period must also be raised from 7 days to 10 days in case of
storage of export cargo irrespective of place of storage.
(vii). The port is empowered to sell the
goods already sold in auction but not cleared from the port premises within 30 days. Why should the port increase demurrage on such
goods? The proposal deserves to be withdrawn.
(viii). While concession has been granted to
containers, no concession has been given for containerised cargo. Ground rent shall not be charged on cargo also.
(ix). If the port is charging
ground rent, it shall not charge demurrage.
(x). For general cargo, there shall be 7 free days.
(xi). The free period of 3 days
for import is in order. In all genuine cases, cargo is cleared in 3 days.
The Indian National
Shipowners Association (INSA)
(i). There shall be a
fixed transhipment cost.
(ii). Wharfage on
containerised cargo shall be abolished. Wharfage
must be only on containers.
The Shipping Corporation of
India (SCI)
(i). We agree with
the views expressed by the representative of INSA and BCHAA.
(ii). In the case of
transhipment cargo, there shall be either wharfage or ground rent and not both.
The Container Shipping
Lines Association (CSLA)
We agree with the views of INSA
and BCHAA.
Mumbai and Nhava-Sheva Ship
Inter-Modal Agents Association (MANSA)
(i). There is no
congestion at the Mumbai Port Trust. There
is, therefore, no case for increasing free days for import of break bulk cargo.
(ii). Wharfage can be only
on container or containerised cargo and not on both.
8.
The
proposal was further examined and the MBPT was requested to furnish certain clarification
/ additional information. The MBPT vide its letter No.FA/ACC/212(V)/5820 dated 7 April
2000 furnished its comments.
9.
With
reference to the totality of information collected during the processing of this case, and
based on a collective application of mind, the following position is seen to emerge:
(i). The MBPT has
proposed to regroup the commodities in the wharfage
schedule and prescribe only 10 rates in the revised schedule. This proposal is stated to be for the purpose of
further simplification of the wharfage schedule. However,
a perusal of an impact statement forwarded (at our instance) by the MBPT showing the
item-wise traffic and the wharfage in the existing rates and the proposed (regrouped)
rates for the year 1998-99 and 1999-2000 shows that the regrouping results in an increase
of revenue to the tune of 7.5% in 1998-99 and 0.25% in 1999-2000. The proposed regrouping
results in steep increase in the wharfage rates for certain commodities. The logic for
such regrouping is not evident and the resultant advantage is not apparent. The proposed changes are seen to result in steep
hikes in some cases because of the regrouping proposed.
While any
proposal for rationalization / simplification of the tariff schedule is acceptable, the
logic of the approach adopted in this case is not clear and commonly understood. In this case, the need for reducing the 11 items
charged on weight basis and the justification for achieving this by shifting some items to
the ad valorem category has not been explained.
The MBPT must set out these details clearly.
Until this is done to the satisfaction of this Authority, the existing
schedule will continue with its 14 items.
The impact
assessment furnished by the MBPT in response to our request is quite revealing. It
will be useful for the MBPT to share this assessment with the users so that they can also
give meaningful responses to the changes contemplated.
It is recognized in this context that, at the time of previous
rationalization, the MBPT had so consulted with its users.
(ii). The proposal of the
MBPT is to charge wharfage on POL and products handled at the docks at the same rates
applicable for such commodities handled at the Marine Oil Terminal (MOT). Since the quantity of POL and the product handled
at the docks is not very high and the rates charged at the MOT are already approved and
included in the Scale of Rates of the MBPT, the proposal of the MBPT is approved.
(iii). The MBPT has proposed to
allow a rebate of 20% in wharfage charges on coastal cargoes handled at the port. In line with the policy of the Govt. of India to
encourage coastal shipping, the Authority has so far been allowing concession to coastal
vessels in vessel-related charges; there is no provision for concessions in cargo related
charges. The matter of extending concession
in cargo-related charges for coastal traffic is an issue of common concern to all the Port
Trusts; and, as an issue on which separate decisions in respect of individual Port Trusts
can give rise to avoidable conflicts of interests. The
Authority is also aware that some of the Port Trusts are opposed to the principle of ports
subsidizing coastal traffic for easing pressure on road / rail traffic. That being so, it will be desirable for the MBPT
to get its proposal, of giving 20% concession in cargo related charges ostensibly for
encouraging coastal traffic, to be discussed in the forum of the Indian Ports Association
so that a coordinated appraisal of its implications can emerge for final consideration.
(iv). During the joint hearing,
the BCHAA pointed out that the levy of wharfage on imported cargo allowed to be stored in
bonded warehouses is not made with the sanctity of Government approval. However, as indicated by the MBPT, the existing
rate was implemented with effect from 1991 and has been in force for nearly 10 years now. This Authority, therefore, does not wish to
enquire into the legal validity of the existing rates. It
is for the aggrieved party to challenge levy of such charges in the appropriate court of
law. Since the rate is already in existence
for the last 10 years and the proposal of the MBPT is to round off this rate and include
it in the DSR, the proposal is approved.
(v). The proposal of the
MBPT to levy wharfage on bottom cargo that remains on the wharf for more than 24 hours, at
the rates as applicable to the transhipment cargoes is approved.
(vi). The proposal of the MBPT to
levy wharfage on ship-to-ship transhipment cargo and on cargo received for transhipment by
road is similar to the wharfage charges applicable for cargo moved to bonded warehouses. This proposal of the MBPT relating to wharfage on
transhipment cargo is approved.
(vii). The MBPT has proposed to reduce
the slabs of period in the demurrage schedule and also to revise the existing minimum rate
of demurrage by 20%. It has been pointed out
that the reduction in slabs is based on the recommendations of a Committee, which included
representation from port users also. The MBPT
has further added that 73% of the total packages discharged during 1998-99 was cleared
within the free period. During the Joint
Hearing no user organisation raised any objection to this proposal. Therefore, the proposal of the MBPT in this regard
is approved.
(viii). The MBPT has proposed to give additional
free days in the case of cargo retrieved from sunk or grounded vessels in order to
encourage speedy clearance of cargo in such cases. It
has been mentioned that cargo in such cases gets damaged and additional formalities are
required to be finalised before the consignees are able to effect clearance. The additional 7 days free period proposed for
such cargo by the MBPT is approved.
(ix). In the existing DSR, a
concessional demurrage of 1/8th of the demurrage for 90 days from the expiry of LFD of the
vessels is levied on all goods shown as excess in the out turn of the vessel. The MBPT has argued that consignment loaded for
discharging at Mumbai Port but not entered in the Import General Manifest (IGM) cannot be
treated as excess landed cargo and the benefit of concessional rate shall not be extended
in such cases just because the cargo has not been included in the IGM. The MBPT has pointed that if the Bill of Lading
shows that the cargo is to be discharged at Mumbai Port the intention is clear whether the
IGM contains the item or not. The MBPT has
accordingly proposed to delete from the DSR the clause extending such concession to the
excess landed cargo from the DSR.
During the joint
hearing, the BCHAA objected to the deletion of the existing provision from the DSR. It argued for grant of an additional entry in the
IGM. It has pointed out that the trade shall
not be made to pay more for somebody elses error.
It is to be
recognised that if the cargo had been included originally in the IGM, the trade would have
paid the normal demurrage charges. For the omission on the part of the Shipping Lines /
Agents, the port cannot be required to extend concessions.
The importer may have to settle the issue with the Shipping Lines / agents. Due to improved communications system, the details
of the cargo to be discharged can be had before the actual arrival of the ship. Accordingly, the ship agents can take advance
action to get the items added in the IGM, with reference to the Bill of Lading. Viewed in this perspective, the proposal of the
MBPT in this regard is also approved.
(x). The MBPT has proposed
to do away with the existing system of charging only 20% of the demurrage fees of goods,
detained by the Customs for such examination involving analytical or technical tests other
than the ordinary process of appraisement and to place such cases before its board for
consideration of remission under Section 53 of the MPT Act based on the merits of the
individual cases. During the Joint Hearing,
the BCHAA pointed out that withdrawal of concession of demurrage on goods detained by the
Customs amounts to increase in the rates.
In a similar
case relating to the Chennai Port Trust (CHPT), the Authority has passed an order
prescribing a graded scale of levy of demurrage.
There appears no
merit in withdrawing the provisions already available in the Scale of Rates under the
arguments to consider such cases for waiver under Section 53 of the MPT Act. Since the
graded scale of demurrage prescribed by the Authority appears to have been well accepted
and well settled, there can be no reason why a similar system cannot be made applicable in
the case of MBPT also. However, considering
the differences in the demurrage schedules between the CHPT and the MBPT, suitable
adjustment in the slabs of demurrage period is required to be made. Further, recognising the scope for collusion of
various vested interests, the concessional demurrage is restricted to 60 days only.
Accordingly, following clauses are approved to be incorporated in the DSR in this
connection:
13.(a). Periods during which the goods are detained by the
Commissioner of Customs for the purpose of special examination involving analytical or
technical test other than the ordinary process of appraisement and certified by the
Commissioner of Customs to be not attributable to any fault or negligence on the part of
the Importers; and,
(b). Where goods are detained by the Commissioner of Customs on
account of Import Control formalities and certified by the Commissioner of Customs to be
not attributable to any fault or negligence of the port of the Importer, for such period
detention under (a) and (b), the demurrage charges shall be recovered as under:
First 30 days
of detention : 20% of applicable demurrage
31st day to
60 days of detention : 50% of the applicable demurrage
61st day
onwards of detention : 100% of the applicable
demurrage.
(xi). The MBPT has proposed to
prescribe a uniform free period of 7 days for the export cargo irrespective of the place
of storage. The Port has also proposed to
provide pre-shipment storage facilities for aggregation of export cargo for carrying out
Custom examination and preparing pallets and to allow a demurrage free period of 30 days
from the date of receipt of export cargo at an area earmarked for this purpose. Some of the users have welcomed the move of MBPT
to allow the 30 days free period for aggregation of export cargo but objected to the
reduction of 10 days free of demurrage allowed earlier to those cargo stored in the open
yard in docks to 7 days. Considering the
concession of 30 days free period for carrying out pre-shipment formalities and
aggregation of cargo, the proposal of MBPT to prescribe a uniform 7 days free period for
the export cargo stored in the docks is approved.
(xii). The MBPT has proposed to increase
the demurrage charges on goods sold in auction but remaining uncleared beyond the
permissible free period. The intention of selling the goods in auction is to de-congest
the port. If, even after such auction, the
buyer in the auction is not clearing the goods, the desired results cannot be achieved. Further, MBPT has pointed out that the present
rates were fixed nearly two decades ago. During the Joint Hearing, the BCHAA pointed out
that the port can auction the goods after 30 days and that being so, why the demurrage
should be increased. The BCHAAs
objection is perhaps misplaced. The case is not for increase in demurrage on cargo to be
paid by the importer or exporter; the proposal is only for increase in demurrage of goods
sold in auction and not cleared within a prescribed period.
These charges are to be borne by the buyer of such goods in the auction. That being so, this proposal of the MBPT is also
approved.
(xiii). For the purpose of clarity, the MBPT has
proposed to define the over-dimensional packages in DSR amending the existing provisions. The amendments as proposed by the MBPT are
approved.
(xiv). The MBPT has proposed to dollarise the
consolidated wharfage on transhipment cargo inside the transhipment container. The MBPT has argued for dollar denomination
stating that the payment is to be made by the Vessel Agents who recover it from the
consignees of the transhipped cargo in the form of freight in US $.
The MBPT
proposal to denominate in dollar terms this consolidated wharfage deserves to
be singled out for specific rejection. Cargo
related charges have nowhere come to be denominated in dollar terms. It is the
consistently stated position of this Authority not to veer away from this principle.
Significantly, even in the case of the PSA SICAL Terminal at the Tuticorin Port Trsuts
(TPT), consolidated wharfage for containerised transhipment cargo has been
denominated onely in rupee terms.
In fact,
unqualified denomination in dollar terms even of the wharfage on transhipment containers
will give rise to some (legal) inconsistencies. Container
handling charges had come to be denominated in dollar terms on the strength of a legal
fiction that a container was an extension of the hatch of a vessel. If, on the strength of
this logic, denomination in dollar terms of the wharfage on transhipment containers is
allowed, then, where coastal vessels carried the said containers, it would have to be seen
as a case of an extension of the hatch of a foreign going vessel in a coastal vessel! For this reason, therefore, as has been done in
the case of the PSA SICAL Terminal, wharfage on transhipment containers will have to be
denominated both in dollar terms and rupee terms.
The MBPT has
proposed a rate of US $ 57 for transhipment cargo inside a container having length upto 20. Since dollarisation of this rate is disallowed, it
is necessary to prescribe a rupee rate for consolidated wharfage for transhipment cargo in
containers.
The port has,
perhaps, worked out the (proposed) dollar rate by converting the existing rupee rate of
Rs.1200/- applying the exchange rate as on 30 June 1991, following the instructions issued
by the Government of India earlier in this regard. However, if the current exchange rate
is applied of the (proposed) dollar rate, the Rupee rate works out to around Rs.2500/-. This is close to the rates proposed by the MBPT
for consolidated charges on FCL moving through the private CFSs.
The break up of
calculation of this rate (as provided by the MBPT) indicates that a sum of Rs.300/- (per
TEU) is included for provision towards displacement of labour. In fact this cost is to be spread over the entire
activities of the port and not be confined only to the container handling. This approach has been adopted by the Authority to
deal with labour redundancy in the case of fixing handling cost of export of Manganese Ore
through the Visakhapatnam Port. In the same
analogy, the cost of displacement of labour should be spread over the entire general cargo
handling activities including obviously this activity also. That being so, only a part of
such cost will be allocated to this activity.
Accordingly, the
revised cost is worked out as follows:
(i). |
Wharfage
charges on cargo inside a 20 feet container (Average wharfage: Rs.106/tonne Average
weight:18.5 MT) |
Rs.1,960.00 |
(ii). |
Contingency
for inflation, wage increase, partial allocation of cost of displacement of labour, etc.,
@ 10% p.a. for the next two years |
Rs.411.60 |
|
|
Rs.2371.60 |
|
Say Rs.2400.00 |
|
Similar rates
are also approved for cargo inside containers moving through private CFSs.
(xv). The following proposals of the
MBPT are also approved,
(a)
recovery of charges in respect of import loaded containers discharged at other
Indian Ports and brought to Mumbai by rail or road for effecting clearance;
(b)
charges on containers stuffed in the Mumbai Port premises and removed for shipment
from other ports; and,
(c)
charges on containers received in Mumbai Port duly stuffed in areas other trans
Mumbai Port and removed for shipment through Ports other than Mumbai.
(xvi). The proposal to prescribe a uniform
wharfage charge per TEU, irrespective of the nature of cargo, on containers moving from
the port premises to private CFS is approved subject to modification of rates as given
under paragraph 9(XIV) above.
(xvii). The MBPT has proposed to exempt payment of
licence fees on the customs detained containers stored at the area allotted by the Board
to the Customs on rental basis. This proposal is approved.
As regards cargo inside the container, the graded scale of demurrage levy as
prescribed in paragraph 9(x) can be made to apply.
(xviii). The MBPT has proposed to replace in the DSR the
words Docks Manager wherever they occur by the words Traffic Manager. This is, perhaps, due to re-designation of the
post of the Head of Traffic Department; and, hence is approved.
(xix). In the existing DSR, container related
charges are prescribed in two slabs viz., containers having length upto 20
and over 20 and upto 40 in Section V at many places. To
obviate difficulties in charging containers of 45 length, the port has proposed to
change the wordings as containers having length upto 20 feet and containers
having length over 20 feet. It will be
better to introduce a third category of containers having length over 40 feet and
prescribe a rate therefore. This is the
practice adopted at most of the Ports. However, the MBPT has stated that the number of 45
feet containers handled at its Docks is insignificant and incorporating a separate rate
for containers having length over 40 is not considered necessary (by it). This Authority accepted the explanation offered by
the MBPT; and, approves its proposal in this regard.
10.
In
the result, and for the reasons given above, and based on a collective application of
mind, the proposal of the MBPT for rationalisation of rates under Section I to III and V
of its Dock Scale of Rates is hereby approved by this Authority subject to the specific
decisions and modifications indicated in paragraph 9 above.
11.
The
amended Section I to III and V of the Dock Scale of Rates of Mumbai Port Trust is attached
as Annex.
12.
This
Order shall come into effect immediately after its notification in the Gazette of India.
S.Sathyam, Chairman
[Advt./III/IV/Exty./143/2000]
ANNEX
SECTION I
The existing rate
Nos. 9 (i), (ii) and (iii) in the schedule of Dock wharfage rates are deleted and
substituted by the following:
Rate No. |
Description
of Goods |
Basis of charge |
Import |
Export |
|
9 |
|
|
|||
|
(i) |
Crude Oil |
Tonne |
38.00 |
38.00 |
|
(ii) |
Kerosene and Light Diesel Oil |
Tonne |
25.00 |
25.00 |
|
(iii) |
All other POL Products |
Tonne |
44.00 |
44.00 |
The existing
General Notes Nos. 4, 5, 8 and 10 are deleted and substituted by the following:
4.
No Docks Wharfage will be levied
on cargo discharged from one hatch of a vessel and reshipped in another for trimming or
rearranging the vessels cargo either by
lighters from overside or over the Docks wharves,
provided in the latter case it is not allowed to remain on the wharf for over 24 hours and
Boards labour is not utilised. Whenever
such cargo remains on the wharf for more than 24 hours, charges applicable to transhipment cargo as
provided in General Note 8 shall be recoverable.
5. Dangerous, explosive and inflammable goods landed at the Docks contrary to the Docks Bye-Laws and / or the circulars issued by the Traffic Manager must be immediately removed by the Master / Owners / Agents of the vessel to the Boards warehouses earmarked for such goods, failing which they shall be removed by the traffic Manager at their risk and cost and, in addition, a charge of Rs.500 per package will be levied.
8. Transhipment Cargo:
Wharfage at the rate of Rs.90 per tonne in the case of transhipment by sea and Rs.38 per tonne in the case of transhipment by road shall be levied and demurrage on expiry of free days as per Clause (4) of Section II A Imports will be charged.
10. In respect of Iron and Steel Materials, shifting of cargo from the wharf (hook point) to the storage point will not be undertaken by the Mumbai Port Trust
The following General Note is added:
11. Wharfage at the rate of Rs.38.00 per tonne shall be levied on the cargo cleared from the Dock under Section 49 of the Customs Act 1962. Demurrage on expiry of free days as per clause (4) of Section II A Import shall be levied.
SECTION II
LANDING
DATE FREE DAYS AND DEMURRAGE CHARGES
A.
IMPORTS :
The existing
General Note No.1 General Landing Date is deleted and substituted by the
following:
1. GENERAL LANDING DATE
The Traffic Manager shall declare the General Landing Date for cargoes discharged from a vessel which, save as hereinafter provided, will be the day on which not less than two-thirds of the vessels cargo has been discharged, as intimated by the vessels Master or Agents. For this purpose, the quantity of cargoes discharged after 5.00 p.m. on that day shall be omitted. Cargo intended for overside discharge, if it exceeds the quantity for shore discharge shall be excluded from the vessels cargo for arriving at the GLD of the vessel. Cargo which must be fumigated prior to discharge ashore shall be excluded from the vessels cargo for arriving at the GLD of the vessels.
If the General Landing Date, as computed above falls on a Sunday or on Dock Holiday declared under Docks Bye-Law No.118, the next working day shall be declared as the General Landing Date.
2.
SPECIAL LANDING DATE
The
existing Note 2 (iv) and (vii) are deleted and substituted by the following:
(iv).
Excepting those mentioned at (i), (ii) and (iii) above, where half the consignment or more is discharged
after the General Landing Date is declared for the vessels cargo --
the date of landing of
two thirds of each such consignment.
Packages and pieces short tallied should
be evenly distributed over the number of days occupied in the discharge of the principal
consignment covered by a single Import Bill of Entry or Transhipment Permit.
(vii). Where any consignment or part thereof of iron and steel weighing less than 1½ tonnes, i.e. bars, rods, hoops, scraps, sheets, plates, etc. is landed from a vessel unmarked or in the opinion of the Traffic Manager so insufficiently marked as to prevent the delivery of the whole consignment.
according to the Bill of Lading and he has, the whole of such consignment sorted according to the sizes as far as possible
the date on which the Traffic Manager shall note that the iron and steel is sorted and ready for delivery.
The existing Note 3 and 4 are deleted and substituted
by the following:
3.
FREE DAYS:
All goods will
be allowed storage in the Docks free of demurrage for three days following the General
Landing Date / Special Landing Date declared in accordance with the sub-clauses 1 and 2
above. In
computing the number of free days, Sundays and Dock Holidays declared under
Docks Bye-Law No.118 as well as any other day
on which Customs Import Duty, whether payable
or not, may not be assessed or received, will be omitted in the case of the goods liable
to duty under the Customs Act, 1962. In
computing the free days on other goods, Sundays and Dock Holidays declared under Docks
Bye-Law No.118 only will be omitted. In
the case of Vessels and Barges sunk or grounded in the harbour alongwith the cargo, storage of the cargoes retrieved therefrom will
be allowed at the Docks free of demurrage for ten working days following the General
Landing Date.
4.
DEMURRAGE:
Class of goods |
How charged |
R A T E |
||
For first 20 days |
For 21st to 40th day |
From 41st day onwards |
||
(1) |
(2) |
(3) |
(4) |
(5) |
|
Rs. |
Rs. |
Rs. |
|
In respect of all goods classified in the schedule of Docks Wharfage Rates in Section I Imports |
Per Tonne per day or part thereof |
30.00 |
45.00 |
60.00 |
NOTE: The personal baggage will be charged at the rate of Rs.12 per tonne per day or part thereof.
The existing Note
No.7 is deleted. The existing Note 8 is
deleted and substituted by the following and renumbered as Note No.7.
7. (a) Periods during which the goods are detained by the Commissioner of Customs for the purpose of special examination involving analytical or technical test other than the ordinary process of appraisement and certified by the Commissioner of Customs to be not attributable to any fault or negligence on the part of the importers; and,
(b) where goods are detained by the Commissioner of Customs on account of Import Control formalities and certified by the Commissioner of Customs to be not attributable to any fault or negligence on the part of the Importer, for such period of detention under (a) and (b), the demurrage charges shall be recovered as under
First 30 days of
detention : 20% of applicable demurrage
31st
day to 60 days of detention
:
50% of the applicable demurrage
61st day onwards of detention :100% of the applicable demurrage
The existing Note 9 is renumbered as Note No.8.
The existing sub
section B Exports: and C are deleted and substituted by the
following:
B.
EXPORTS
Goods for shipment |
Period free of demurrage |
How charged |
||
(1) |
Stored in Docks open yards / or transit sheds |
07 days |
(i). (ii). |
Wharfage as per Section I Exports. A demurrage fee calculated at the rate of 20% of the wharfage fee applicable per day or part thereof. |
(2) |
If not shipped, but removed from Docks into town |
Nil |
(i). (ii). |
No wharfage. A demurrage fee calculated at the rate of 20% of the wharfage fee applicable per day or part thereof. |
(3) |
Cargoes stored in the areas nominated for aggregation of export cargo. |
30 days |
(i). (ii). |
Wharfage as per Section I Exports. A demurrage fee calculated at the rate 20% of the wharfage fee applicable per day or part thereof. |
NOTES:
(i). Shut out cargo must be removed by shippers on receipt of three days notice from the Traffic Manager. In case of non-compliance, the Traffic Manager may remove such goods to a place of storage at the expenses of shippers.
(ii).
In computing the number of free days for
charging demurrage, Sundays and Holidays
referred to in the Docks Bye-Law No.118 will be
omitted.
C.
Goods sold under
Section 61 or Section 62 of the Major Port Trusts Act, 1963, lying uncleared in the Docks
or in other premises in the possession of the Board.
(1). Free Days: All goods sold under Sections 61 or 62 of the Major Port Trusts Act, 1963 will be allowed storage, free of demurrage for five days following the date of confirmation of the sale. In computing the number of Free Days, Sundays and Dock Holidays declared under Docks Bye-Law No.118 will be omitted.
(2). Demurrage: On the expiry of Free Days demurrage will be charged on all goods remaining uncleared until delivery is effected at the rate of Rs.100/- per tonne per day.
If, however,
the goods or a portion thereof remain uncleared on the premises of the Board beyond 15
days following the date of confirmation of the sale,
the sale proceeds of the goods, or if only a
portion of the goods remain to be taken delivery of by the purchaser, the proportionate sale proceeds, shall be forfeited and the goods or a portion
thereof, as the case may be, resold by the Port Trust. The
aforesaid period of 15 days may be extended,
at the discretion of the Traffic Manager, in
suitable cases, for reasons to be recorded in
writing, having due regard to the circumstances
of the case or to the quantity and bulk of the goods to be removed by the purchaser.
Demurrage charges will be assessed on the gross weight of the goods. Gross weight if not in exact multiples of 100 kgs. will be rounded off to the next higher multiple of 100 kgs. for levy of charges.
Section III
Licence
(storage) fees and warehousing charge
The existing sub
section A is deleted and substituted by the following:
(A) Licence (Storage) Fees on Over-dimensional packages stored in Docks, Sheds and Yards shall be payable in lieu of demurrage at the rate of Rs.5/- per sq. mt. subject to minimum of 5 sq. mt. for 30 days following the date from which the consignment is out of custom charge and is ready for clearance subject to the following conditions :
(i) On Over-dimensional packages having length over 13.6 or having width over 10 in the case of packages removed by the Rail.
(ii) On Over-dimensional packages having length over 40 plus the protruding length over and above the motor vehicle allowed by the Regional Transport Authority from time to time or having width more than 8.6 plus protruding width over and above the motor vehicle allowed by the Regional Transport Authority from time to time.
(iii) For the period from LFD till the day on which the cargo is out of Custom charge and from 31st day from the day on which the cargo is out of Custom charge the over dimensional pacages shall accrue demurrage as per Section II A Imports of the DSRs.
Section V
charges on
cargo containers, containerised cargo and
container equipment
In sub section
A, B , C
, D, E, F and G, the description cargo
container having length over 20 feet and upto 40 feet whenever written is deleted
and replaced by the description cargo container having length over 20 feet.
The existing Notes
(iii) and (vi) of below sub section B are deleted and substituted by the
following:
(iii) Licence (Storage) Fees shall be levied on containers whether empty or loaded destined to / received from ICD by rail / road as per Section V (D) (c) below.
(vi). Local empty container transhipped to ICD by rail or received ex-ICD by rail but not for direct shipment shall be charged US $ 24 for a container having length upto 20 feet and US $ 36 for a container having length over 20 feet for handling at RCD and MBPT Railway Haulage. Licence (Storage) Fees on such container shall be payable upto the date on which the container has been allowed by Customs to be transhipped to ICD. Import loaded container manifested as local if subsequently transhipped to ICD shall be treated as local container till the date on which the container has been allowed by Customs to be transhipped to ICD. Similarly ICD import containers destuffed and cleared from the Port shall be treated as FCL for levy of Port charges.
The existing
Sub-Section (D)(c) is deleted and substituted by the following:
(c) |
Empty or Loaded container received from/despatched to ICD by rail/road |
US $ 2.5 per container having length upto 20 and US $ 5.00 per container having length over 20 per day or part thereof after the expiry of two days from the day following the GLD till the date of their loading on wagons / removal by road or from two days following the date of receipt of containers at RCD from the upcountry ICDs or storage yards till the date prior to the date of shipment (i.e. excluding the date of shipment). In case a container is not removed / shipped within 10 days from the day following the GLD in case of import or from the date of receipt in case of export, the Licence (Storage) Fees to be levied will be US $ 5.00 per container having length upto 20 and US $ 10.00 per container having length over 20 per day or part thereof from 11th day. |
NOTES:
(5) The Combined Transport Operators / Masters, Owners or Agents of vessels shall remove the containers to the respective site / yard / destuffing point nominated by the Traffic Manager within a period of 4 calendar days following the GLD of the vessel. If the Combined Transport Operators / Masters, Owners or Agents of vessels fail to remove such containers to the nominated areas within the prescribed period of 4 calendar days, the Traffic Manager shall have the authority to remove such containers to the nominated areas at the risk and cost of Combined Transport Operators / Masters, Owners or Agents of vessels. Removal charges as notified from time to time will be levied on such containers.
(6) Container stuffed in the Port premises / container received in Docks duly stuffed in the areas other than Mumbai Port premises and removed for shipment through Ports other than Mumbai shall be charged Licence fees as per section V (D) (A) above from the day following the date of stuffing / from the date of receipt till the date of removal of container. In the case of containers stuffed in the Port premises containers received duly stuffed in the areas other than Mumbai Port premises and removed to town shall be charged Licence fees of US $ 2.5 for a container having length upto 20 feet and US $ 5 for a container having length over 20 feet per day of part thereof from the day following the date of stuffing / from the date of receipt till the date of removal of the containers. The cargo inside the container shall be charged demurrage at the rate of Rs.800/- per TEU per day or part thereof for the period of its stay in the Port. [No separate wharfage shall be recovered either on such container or on cargo inside the container.]
(7) The Import loaded containers discharged at an Indian Port other than Mumbai and brought to Mumbai by Rail / Road for giving delivery shall be charged Licence Fees as per Section V (D) (a) above. In the case of containers received by Rail, handling charges of US $ 60 per TEU shall be levied. Demurrage on the cargo inside the containers shall be charged in terms of clause (4) of Section II A Imports from the date of receipt. No wharfage on the cargo inside the containers shall be levied.
(8) No Licence (Storage) Fees shall be levied on containers loaded with cargo and seized / detained by the Customs / DRI / CIU etc. from the day of its removal to the area allotted by the Board to the Customs for storage of such containers. Demurrage on the cargo inside the container shall be leviable as per clause (7) of Section II A Imports of the DSRs.
(9) Any consignee desires to clear FCL through private CFSs within or outside jurisdiction of the Commissioner of Customs, Mumbai shall remove the containers within 7 working days following the GLD declared for the vessel. On the cargo inside the container a consolidated charge of Rs.2400/- for a container having a length upto 20 feet and Rs.4800/- for a container having length over 20 feet shall be recovered. In case container is not removed within the said period of 7 working days the demurrage charges at the rate prescribed in clause 4 of Section II of the DSR shall be levied on the cargo inside the container.
(10) Demurrage charges on the cargo stuffed inside the container and subsequently destuffed and removed back to town shall be levied as per (6) above. No wharfage shall be levied thereon. Similarly, in the case of cargo stuffed inside the container and subsequently destuffed and again restuffed in the container and shipped on board the vessel, demurrage charges shall be levied as per (6) above till the date of restuffing of cargo inside the container and wharfage in terms of Section I Exports shall also be levied on cargo inside the container.
In Clause (4) of
sub section E, the word Docks Manager is substituted by Traffic Manager
(G)
Charges on
Containerised Cargo:
The existing Clause
(1), 3 (i) and 3 (v) are deleted and substituted by the following:
(1) Wharfage and demurrage shall be payable on import containerised cargo, excepting those destined to ICD and the FCLs cleared through Private CFS in terms of note (9) to sub-section D above as applicable under Sections I and II. On transhipment cargo in containers a consolidated wharfage at the rate of Rs.2400 for a container having length upto 20 feet and Rs.4800 for a container having length over 20 feet shall be payable but no demurrage shall be levied thereon.
(3) (i) In the case of containers, other than that destined to or received from ICD, transhipment containers, and the FCLs cleared through Private CFS demurrage on cargo in container shall not accrue for 7 working days in respect of FCLs and LCLs following the GLD of the vessel.
(v)
If the FCL
container, other than that destined to or
received from ICD, transhipment containers and
the FCLs cleared through private CFS, having
reached the notified area has not been destuffed for no fault of the consignee, the consignee will be entitled to a remission
in demurrage charges on obtaining the endorsement on the Bill of Entry as under:
|
Conditions to be fulfilled |
Endorsement of the B/E by the Docks
Official |
Non-Accrual of demurrage |
|
|
|
|
(b) |
B/E to be presented with Out
of Customs charge endorsement / ready for
clearance. |
Endorsement Cargo not destuffed (reasons for not destuffing the container should be recorded in writing) to be made by the Shed Supdt. and signed by Asstt. Manager. |
3 calendar days including the date of presentation of B/E. |
(c) |
On presentation of B/E on the 2nd occasion to the Shed Supdt. with endorsement of Customs Out of charge ready for clearance on the 4th calendar day mentioned in Col. (3) against (b) above. |
Endorsement Cargo not made available for delivery within the period of 3 calendar days as container could not be destuffed (reasons to be recorded in writing) to be made by the Shed Supdt. and signed by the Asstt. Manager. |
3 calendar days beyond the period as at (b) above. |