(Published in Part – III Section 4 of the Gazette of India, Extraordinary)
| No. 15 | NEW DELHI, 22th JANUARY, 2001 |
Tariff
Authority for Major Ports
NOTIFICATION
In exercise of the powers conferred by Section 48 of the Major Port
Trusts Act 1963 (38 of 1963), the Tariff Authority for Major Ports hereby
approves the proposal of the COPT on volume discount and concession arrangement,
as in the Order appended hereto.
( S.
Sathyam )
Chairman
Case
No.
TAMP/105/2000-COPT
The
Cochin Port Trust (COPT)
…
Applicant
O R D E R
(Passed
on this 5th day of January 2001)
This case relates to a proposal on volume discount and concession
arrangement from the Cochin Port Trust (COPT).
2.
The COPT in its proposal has stated that it is the only major port in
India having a narrow hinterland, which is often shared, by neighbouring ports
like New Mangalore Port Trust (NMPT) and Chennai Port Trust (CHPT).
So as to attract more volumes, the Port has considered to have some
flexibility in its tariff and offer concessions in certain handling costs /
cargo related charges.
3.
Based on the views expressed by several port users during the joint
hearing set up by the TAMP on 11 August 2000 in the case relating to fixation of
consolidated handling charges for transhipment containers, the COPT Board in its
meeting dated 30 August 2000 decided to grant certain rebate / refund on
wharfage of export / import cargo in order to attract more volume of cargo to
the Cochin Port. The COPT has
submitted the following proposal on volume discounts:
(i).
Any exporter / importer who exports / imports higher volume of containers
shall be entitled for a refund of Rs.500/- per TEU on the additional throughput
handled through Cochin Port over and above their highest normal throughput
handled during previous 2 financial years.
For the above purpose the “financial year” means “1st April of the
year to 31st March of the next year”.
(ii).
Any cargo, other than containerised cargo, crude and POL products, which
was not handled in the Port of Cochin during the last two financial years, and
if such cargo is imported / exported through Cochin Port during any financial
year, (after two financial years),
that cargo shall be entitled to a 25% refund in the wharfage till the end of
that financial year.
(iii).
Refund application in the prescribed format with all relevant details may
be submitted by the Importer / Exporter to the Traffic Manager as and when
refundable or within 60 days from the end of that financial year.
4.1.
A copy of the proposal was circulated to the main port users and
representative bodies of port users for their comments.
The Cochin Steamer Agents’ Association (CSAA) and the Cochin Customs
House Agents’ Association (CCHAA) have fully agreed with the proposal.
The Shipping Corporation of India (SCI) had no comments to offer in this
regard as the concession pertains to cargo interest to offer incentive to
shippers to use the Cochin Port.
4.2.
While welcoming the proposal, the Indian National Shipowners’
Association (INSA) requested that some rebates / discounts on similar lines
should be extended on ship-related costs also.
5.1.
A joint hearing in this case was held on 19 December 2000 in Cochin.
During the joint hearing following submissions were made:
Cochin Port
Trust (COPT)
(i).
We want to introduce incentives through volume discounts as advised by
the TAMP.
(ii).
We want to use this incentive to attract new cargo and not to waste time
on the existing cargo.
(iii).
Our focus is on shippers not Lines.
We want the incentive to go to consignee; Lines may or may not pass on
the benefit.
(iv).
In our judgment, one year concession is sufficient. This volume discount is only to attract shippers from other
ports. We may not be able to offer
this volume discounts for more than one year.
(v).
Port does not charge notional costs like pool levy.
(vi).
POL products that are ‘new products’ can be given the benefit but the
existing POL products under the disguise of a different nomenclature should not
be projected.
Kochi Refineries
Limited
(i)
Wharfage on crude and POL products are very high and required to be
reviewed.
(ii).
We must also get rebates / concessions.
We will be exporting furnace oil soon and that must get concession.
Therefore, include “POL products” in the list of new cargo.
(iii).
POL products are few and hence, there is no scope for manipulation.
We
will give a complete list of POL products so
that there is no scope for manipulation to claim discounts through a mere change
of nomenclatures.
The Cochin
Steamer Agent’s Association (CSAA)
(i).
New comers will benefit. Old
loyal users will get nothing. This
is anomalous.
(ii).
Give the incentive to Lines since they will be able to influence new (and
more) cargo better.
Container
Shipping Lines Association (India)
(i)
It will be more meaningful to go on ‘slab rates’.
(ii).
Notional costs like Labour pool levies increases our costs. There must be time bound action to do away with these costs.
(iii).
We endorse the CSAA’s suggestion of giving some benefit to the Lines as
well.
The Cochin
Customs House Agent’s Association
(i).
The scope of the proposed Scheme needs to be widened.
(ii).
This is a one time ‘incentive which is enough to attract the shippers
for the first time. This may not be
adequate to retain them. Therefore,
give volume discounts for a longer period.
(iii).
Give incentive to Custom House Agents also.
Indian National
Shipowners Association
Volume discounts may be considered on fresh water.
6.
With reference to the totality of information collected during the
processing of this case, the following position emerges:
(i).
This proposal can be seen as a tariff incentive scheme to attract new
cargo and not as a volume discount scheme.
This position has also been accepted by the COPT.
A volume discount scheme usually means discounts through slab rates (on a
sliding scale) for higher levels of performance or for assured levels of
throughput. In the COPT case
relating to fixing consolidated tariff on transhipment containers, the Authority
had suggested introduction of such a volume discount scheme and not a tariff
incentive scheme as has been proposed now by the COPT.
The tariff incentive scheme proposed by the COPT, however, has been
endorsed by all the users; and, the Port also anticipates additional throughput
of cargo as a result of this scheme. In
these circumstances, the proposed scheme can be considered as an interim measure
subject to review and modification at a later date.
In any case, the tariff incentive scheme proposed now is very simple to
operate and will not result in any loss to the Port’s current revenue since
rebates are proposed to be offered only on new cargo, or additional volume in
the case of containers.
(ii). The proposed scheme does not provide any incentive to retain the existing cargo. As has been pointed out by the COPT, the proposal is to focus on new cargo and not on the existing cargo. This approach in the long run may not yield the desired result of boosting up the Port’s traffic. The Port’s endeavour, therefore, shall not only be limited to attracting new cargo but also to retain the existing level of traffic. The COPT must take this aspect into consideration while formulating a volume discount scheme.
(iii). The shipping interests have requested for extending such an incentive to vessel related charges also. The CSAA and CSLA have mentioned that the Lines will be able to influence new cargo better and hence such incentive should be given to them direct. It is noteworthy that in the NSICT tariff revision case, some of the users have alleged that the Lines do not pass on the concessions given to them by the Terminal Operator. Irrespective of the agency to which such concessions are allowed, the ultimate objective is to reduce the total cost of import / export. The COPT has proposed to pass on the benefit directly to the importer / exporter which is found to be reasonable. To encourage vessel traffic, however, in the modified scheme to be formulated, the COPT may consider discounts on vessel related charges also, if it is likely to bring more traffic to the Port.
(iv). The COPT proposal excludes crude
and POL products. The COPT
apprehension is that the existing POL products under the disguise of a different
nomenclature may claim such discounts on tariff under the proposed scheme.
The KRL has assured that it will give a complete list of POL products so
that there is no scope for manipulation to claim discount through a mere change
of nomenclatures.
While crude oil may be excluded from the scheme being an existing cargo,
such an exclusion of POL products does not tally with the objective behind the
COPT proposal. There may be POL
products, which are new to the Port, and they must also get the benefit of
tariff incentive like any other new cargo.
It is, therefore, reasonable to include the POL products in the proposed
scheme.
The apprehension of the COPT about possible manipulation in the nomenclature of the POL products deserves consideration. The COPT and the KRL shall discuss amongst themselves and jointly prepare a complete list of new POL products likely to pass through COPT in near future. Only ‘new’ products figuring in such a list to be prepared will qualify under the proposed scheme for tariff incentive.
(v). The wording of the scheme
proposed by the COPT requires some modifications to remove ambiguity.
The COPT has proposed that the refund applications are to be submitted by
the importer / exporter ‘as and when refundable’.
What is actually meant is that applications seeking rebate shall be
submitted after completion of the shipment.
(vi). The scheme proposed will allow
shippers to enjoy rebates in tariffs for only one year i.e. during the first
year of their operation. The COPT
has maintained that the period of one year is sufficient by which time the users
can reasonably stabilize their operations through the Port.
This is not a reasonable proposition as volume discount will be available
on a regular basis depending on the volumes handled by the shippers.
The COPT scheme does not, however, recognise the volume of cargo.
It only considers the new cargo passing through the Port.
Since the scheme is an interim arrangement, the proposed approach is
accepted, again, subject to review and modification at a later date.
(vii). A comprehensive revision of the Scale
of Rates of the COPT was ordered by this Authority in Dec. 98 / Jan. 99. In the light of a two year tariff revision cycle prescribed,
the COPT tariffs are already due for further review. The COPT is advised to come up with its proposal for a
comprehensive review of its Scale of Rates.
While formulating such a proposal, the COPT shall incorporate a more
scientific volume discount scheme in place of the interim scheme proposed.
It will be useful for the COPT to formulate such a volume discount
proposal in consultation with its users. Till
formulation of a comprehensive tariff revision proposals including volume
discount scheme, the interim tariff incentive scheme proposed by the COPT is
approved to operate.
7.
In the result, and for the reasons given above, and based on a collective
application of mind, this Authority approves the proposal of the COPT on volume
discount and concession arrangement and directs the COPT to insert the following
provisions in its Scale of Rates appropriately:
“Volume Discount and Concessions
:
1.
Containers.
Any importer / exporter shall be entitled for a rebate of Rs. 500/- per
TEU on the additional throughput handled over and above their highest throughput
handled during the previous two financial years.
2. Bulk,
Break Bulk and Liquid Cargo.
Any cargo, other than containerized cargo and petroleum crude, which was
not handled in the Port during the last two financial years, is imported /
exported through Cochin Port, that cargo shall be entitled to a 25% rebate in
the wharfage till the end of the financial year in which the traffic has been
handled in the Port.
Note: (i). For the above purpose, the financial year means 1 April of a year to 31 March of the next year.
(ii).
Rebate applications on account of clause 1 and 2 above from the importer
/ exporter shall be submitted to the Traffic Manager after completion of
shipment or in any case within 60 days from the closure of that financial
year”.
( S.
Sathyam )
Chairman