(Published in Part – III Section 4 of the Gazette of India, Extraordinary)
| No.79 | NEW DELHI, FRIDAY, JUNE 9, 2000 |
Tariff
Authority for Major Ports
Notification
No.TAMP/2/2000-KPT - In exercise of the powers conferred by Section 49 of the Major Port Trusts Act, 1963 (38 of 1963), the Tariff Authority for Major Ports hereby disposes of the application made by M/s. Petronet V.K. Limited for framing a Scale of Rates for Way Leave Charges for laying the pipeline in the land limits of the Kandla Port Trust, as in the Order appended hereto.
SCHEDULE
Case No. TAMP/2/2000 - KPT
M/s. Petronet V.K.
Limited
Applicant
V/s
The Kandla Port Trust
(KPT)
Respondent
O R D E R
(Passed on this 11th day of May 2000 )
This case
relates to an application submitted by M/s. Petronet V.K. Limited (PVKL) for framing a
Scale of Rates for way leave charge for laying the pipeline in the land limits of the
Kandla Port Trust (KPT).
2.
In its
submission, the PVKL has made the following points:-
(i). M/s. Petronet
V.K. Limited is a company incorporated under the Companies Act, with majority equity
participation by Petronet India Limited and M/s. Indian Oil Corporation Limited (IOC). The Company is a Special Purpose Vehicle
incorporated under the directives of Government of India with the main object of laying,
maintaining and operating a petroleum carrying pipeline from Vadinar / Jamnagar to Kandla
(VK pipeline).
The VK pipeline
will pass through,
Ø land belonging to or
administered and controlled by the Gujarat Maritime Board;
Ø the sea bed within the
territorial waters of India in the Gulf of Kutch;
Ø land vested in the KPT; and,
Ø land belonging to private
owners.
(ii). The most optimal and
cost-effective route for constructing the VK pipeline would pass through for a distance of
about 9.3 km. in Kandla Port limit.
(iii). The Ministry of Petroleum
and Natural Gas has requested the Ministry of Surface Transport (MOST) to expedite
approval for laying the pipeline through the limits of the KPT.
(iv). On receipt of a
communication from the KPT granting approval for laying and commissioning of VK pipeline
with a proposal to charge Rs.18/- PMT of the throughput per annum as Facility compensation
Charge (FCC). The Oil Co-ordination Committee
conveyed it views against the concept of levying of FCC by the KPT.
(v). PVKL also represented
to the KPT against any FCC citing the precedent of the MOU between KPT and M/s. Essar Oil
Limited. In the case of the VK pipeline, neither is any facility required to be created in
the KPT area nor is any regular port related service required to be provided.
(vi). PVKL requested the KPT to
apply way leave charges as in the case of the Kandla-Bhatinda pipeline of the IOC (i.e.,
Rs.8.50 per sq. mtr. per annum), and not to levy FCC. If the KPT was unable to accede to
their request on FCC, the PVKL requested the KPT that the issue and its quantum be
referred to the TAMP for a final decision.
(vii). The KPT, instead of taking up the
matter with the TAMP, informed of an enhancement of the FCC from Rs.18/- PMT to Rs.35/-
PMT on the ground that the KPT would lose revenue after the pipeline was laid and
commissioned. The KPT also restricted them to
handle only products refined at EOL and RPL and insisted the PVKL to pay lease rent and
premium as in the case of a regular lease although the pipelines would be laid
underground.
(viii). If PVKL is compelled to pay the rates as
demanded by the KPT, the pipeline will become economically unviable.
(ix). In view of the position,
PVKL has made the following requests:
(a). The KPT may be directed and ordered not to prevent PVKL in
any way from continuing with the works of laying the VK pipeline, its commissioning,
maintenance, and use.
(b). The TAMP may frame a Scale of Rates for Way Leave Charges
for laying the pipeline in the land limits of KPT.
(c). The KPT may be directed not to levy any FCC for laying,
commissioning, and maintaining the pipeline facility within KPT limits.
3.
The proposal of
the PVKL was sent to the KPT for its comments. In
its reply, the KPT has made the following observations:
(i). The draft MOU
could not be finalised due to non-settlement of contentious issues.
(ii). The (Port Trust) Boards
discretion to frame the terms and conditions in accordance with the provisions of the MPT
Act, 1963 in public interest and in the interest of the port is not hampered by any
amendment to the Act. The Port Laws
(Amendment) Ordinance 1997, while describing the role of the TAMP no way issues any
direction in respect of TAMPs role in execution of contract or permission to execute
the work even before the contract is executed.
(iii). Substantial revenue as well
as turn-over for the KPT comes from handling of POL products at its jetty specially
created for this purpose; out of the total operating income of Rs.171.45 crores, as much
as 52.11% comes out of handling of POL products at Kandla.
Once the pipeline facility is available, the POL cargoes will move through
the pipeline; and, the five jetties of the KPT created at a huge cost will remain idle to
quite an extent, since the other liquid cargoes constitute only a small proportion of the
traffic. Therefore, this revenue accruable
from the PVKL is of utmost importance. If the
PVKL had, at the time of asking for provisional permission, mentioned that they could not
give any Facility Compensation Charges, the KPT would not have given permission for laying
of pipeline in its water and land limits.
(iv). As per the Guidelines issued
by the TAMP, the prayer sought by the PVKL does not actually fall under its purview. The TAMPs basic function is to hear the
concerned parties and, after taking into consideration the prevailing circumstances in a
Port, determine the actual rates or charges for the services to be rendered by the Port
and for the Ports properties. In view of the above, the prayer made by PVKL seeking
direction against the KPT is untenable.
(v). There is no need to
frame a separate Scale of Rates for Way Leave Charges for laying pipelines in the land
limits of the KPT; the rates applicable for allotment of land can be adopted for the
purpose. There is no other alternative for
the KPT than to charge the appropriate rate as Way Leave Charges and PVKL may by requested
to pay the Way Leave Charges as per the Government guidelines.
(vi). The KPT has invested
substantial amount for creation of facilities for handling POL products and is incurring
substantial amount for up-keeping, maintenance and operation of above said facilities.
(vii). Whatever quantity is going to be
handled through PVKL is a direct loss of traffic to the KPT. POL imports which were to the
tune of 115.03 lakh tonnes in 1998-99 are estimated to be at 20 lakh tonnes only, during
1999-2000, showing a reduction of approximately 82.61%. At present, the income pattern for
handling POL products is at the rate of Rs.68/- per tonne.
To compensate the loss of revenue for providing all the above facilities and
the opportunity loss to be suffered by KPT, the KPT proposes to charge only Rs.35/- per
tonne for transporting the oil through PVKL.
(viii). The submission made by the PVKL is that
the FCC is being envisaged to recover for the right of way granted in the waters of Kandla
Port Trust is incorrect. The charges are to
be recovered for the opportunity loss to the KPT by way of royalty (termed as FCC).
(ix). The KPT has always been
maintaining that the FCC has to be settled between the parties; and, the TAMP has no role
in fixing such charges as per the guidelines issued by itself.
(x). Private investors /
operators will be required to approach the TAMP only for tariffs; matters relating to
royalty and upfront payment will have to be mutually settled between them and the Port
Trust concerned.
4.
A joint hearing
in this case was held at the KPT. During the
joint hearing Shri. M.K. Aswani, President, Kandla Port Karmachari Sangh (KPKS) made a
written submission and wanted to join the proceedings on behalf of the KPKS, to protect
the interests of the KPT. This request was
rejected.
5.
Shri. M.K.
Asvani was subsequently included as a Member of the KPT team. He has given a written submission in his capacity
as a Trustee of the KPT. In his written
submission, he has made the following points:
(i). The facility
compensation charges sought for by the KPT from M/s. PVKL is fully justified. In the case of PVKL, whatever product they
evacuate through the proposed pipeline is being handled at the KPT; that much quantity
will, therefore, be reduced from the present volume of traffic being handled by the KPT.
(ii). The KPT will also lose
the traffic of petroleum products as the pipeline will carry the entire petroleum products
from Jamnagar Refineries. Consequently, the Oil Jetties and allied facilities created by
the KPT may remain idle. Thus, in lieu of
loss of revenue, the PVKL is liable to pay the compensation.
(iii). In this case, because of the
unique facility, the user will be benefited. That
being so, there should be a periodical escalation clause of upward revision to fetch
income for the KPT to meet its expenditure.
6.
During the joint
hearing the PVKL has submitted their reply to KPTs comments. The PVKL has requested
that pending final disposal of this dispute, the KPT may be directed to permit them to
resume work on the laying and operations of the pipelines.
7.
In their written
submission, PVKL highlighted the following points:
(i). MOU between any
party and the KPT for use of land at rates and conditions not prescribed by the Authority
(TAMP) is legally impermissible. PVKL have
been consistently requesting the KPT to refer the matter to TAMP. However, the KPT
declined to do so stating that the matter has to be settled only between KPT and PVKL.
(ii). The powers to fix
rates are quasi judicial, which the amended statute has taken away from the Board. The rates proposed to be charged by the KPT are
those said to have been prescribed for lease of land and not for mere right of way. No statement of conditions in respect of these
rates was prescribed by the KPT or approved by the Central Government. A statement of conditions is pre-requisite
statutorily prescribed.
(iii). The mere fact that the KPT
is charging such rates from other pipelines cannot made the practice legally correct, fair
or proper. The reference of TAMP Regulations made by the KPT is relevant in the context of
private investors building new jetties etc. or taking existing jetties on long term lease.
These guidelines have no application to the facts of this case as PVKL is not developing
any port related ship-berthing facility.
(iv). Laying of the pipeline is in
the larger public interest as it will transport oil products at low cost by which the
common consumer will stand to benefit. The
KPT as Trustees of public property must use their property in a manner calculated to
sub-serve the larger public good rather than be driven by profit motive.
(v). The KPT is not
entitled to receive any FCC whatsoever and their demand for FCC is without any authority
and sanction of any law.
(vi). KPTs stand seeks to
completely protect them from competition not only from ports but, from all mode of
transporting of oil and oil products.
(vii). FCC is not charged from pipeline
owners anywhere in the world.
8.
During the joint
hearing the following arguments were advanced by the different parties:
M/s. Petronet V.K. Limited
(i). Reference to FCC
was first noticed by them in the minutes of a December 97 meeting with the OCC. The
pipeline laying started after December 97.
(ii). Terms and conditions
have not yet been finalised by the KPT or Gujarat Maritime Board (GMB). PVKL went by the Kandla Bhatinda pipeline
for the purpose of feasibility studies.
(iii). A reputed international
expert (J.P. Kenny), PVKL Consultant has said that such FCC for crossing channels / waters
is not levied anywhere else.
(iv). Draft MOU was prepared
subject to difference on 2 issues. The matter
was referred to MOST. PVKL wanted the
disagreements to be resolved by TAMP. In
December 98, PVKL asked for permission to lay the pipeline.
The KPT gave conditional permission in January 99.
(v). The KPT Board Note of
December 97 refers to probable loss of business. But KPT did not raise the issue until
16.11.98. On 14.12.98, the KPT asked for an
undertaking; the PVKL gave an undertaking on 16.12.98 to abide by the TAMPs Orders.
(vi). KPTs reply dated 28
February 2000 to TAMP covers only three of the PVKLs prayers. PVKL assumes that KPT accepts other points.
(vii). Cost of oil jetties must have been
recovered long back. The KPT have quoted
todays value of the asset whereas the original investment must have been much less. Going by notified tariff and traffic, the KPT must
have earned at least Rs.60 crores to Rs.70 crores per year. The investment of Rs.3.5
crores on pipeline, which has outlived its life must have earned a lot of profit since
1989. IOC Terminal will remain unaffected, so maintenance cost will not be wasteful.
(viii). Because of two new refineries (Reliance
and ESSAR) additional traffic at Vadinar will be available. (KPT say that traffic at Vadinar will come
irrespective of PVKL). If there is to be any
FCC at all, it shall be nominal and not connected, to per MT. It can be ad-hoc limp sum something
that the PVKL can bear.
(ix). Kandla Bhatinda
pipeline model is available for way leave charges or TAMP may fix any reasonable updated
amount.
(x). They have given the
environmental clearance. The KPT must be
asked to permit them to complete the laying and commissioning of the project.
(xi). The PVKLs traffic
projection is only 5.5 MT per annum for the first five years. The KPT need not project their losses on 9 MT per
year.
The Kandla Port Trust
(i). It is only a
one-metre wide corridor; and, the rate of Rs.16/-, the annual liability will be nominal.
(ii). Two parameters are to
be considered in support of FCC:
(a). Expenditure already incurred by the KPT on the whole
infrastructure.
(b). Recurring O&M cost annually (about Rs.11.5 crores).
(iii). The KPT has given 400 acres
of prime land to the IOC on the expectation of increasing traffic. All that is being nullified now.
(iv). FCC is based on notified
rates. Wharfage alone in Rs.35/- PMT. If pilotage, port due and berth hire are added, it
comes to Rs.68/- PMT. The Port is asking only for Rs.35/- PMT as FCC.
(v). The original quotation
of KPT of Rs.18/- PMT as FCC was with respect to ESSAR MOU.
Besides FCC, ESSAR pays Rs.110 lakhs towards composite charge for lease rent
for waterfront and way leave charge. Apprehension
about GMB charging the same rate is not valid as it is not going to lose any traffic.
(vi). Petronet is as good as a
private company. Still, they have been given
permission on a nomination basis.
(vii). There are many Petronet
subsidiaries. They want to get concessions at
Kandla so that elsewhere they can cite these as precedents.
(viii). When PVKL pipelines are used to the full
capacity, the company will make plenty of profit but the KPT will not ask for increase in
FCC.
(ix). The spin-off loss to
Gandhidham / Kandla areas are substantial (loss of employment in transportation etc.).
(x). MOU should be signed
first. Once the pipeline is commissioned, the
KPT will have no hold at all.
9.
With reference
to the totality of information collected during the processing of this case, the following
position emerges:-
(i). This case
relates to fixation of rates for the use of KPT properties to lay a pipeline from Vadinar
to Kandla by PVKL and decide on the demand of the KPT for a facility compensation charges
(FCC) to compensate the possible loss of revenue, once the pipeline is commissioned.
(ii). The pipeline passes
through the seabed in the KPT waters and through the lands of the KPT.
(iii). There is no dispute
regarding using the seabed in the KPT waters. The
KPT has not demanded any charge for allowing right of way to the submarine pipelines
passing through the seabed. This is reported
to be in accordance with the Geneva Convention of Territorial Sea and Contiguous Zones,
1958, and related Statutes.
(iv). The Applicant-Firm contends
that for laying shore pipeline (underground), the KPT should charge for mere right
of way and not for lease of land. They
have requested the Authority to frame a Scale of Rates for Way Leave Charges for laying
the pipelines in land limits of the KPT.
The KPT
maintains that land allotted for laying pipelines to various agencies is always on the
basis of the corresponding lease rent applicable to the land and its lease rent has
already been approved by the Government / TAMP.
The KPTs
arguments is that no separate Scale of Rates for Way Leave Charges need to be framed and
the existing rates applicable for allotment of land should be applied.
The Authority
has already decided that no concession on Way Leave Charges for laying underground
cross-country pipelines passing through the Port Trusts land need be granted. This decision was taken in a case relating to the
Hindustan Petroleum Corporation Limiteds pipelines passing through the Visakhapatnam
Port Trust land and has already been notified.
That being so,
in the instant case also, there is no need to frame a separate scale for Way Leave
Charges. The existing rates in the schedule
of rents for the KPT lands will apply to the land allotted for laying the underground
pipeline.
(v). As regards levy of
Facility Compensation Charge (FCC), the KPTs argument is that the charge is to be
recovered for the opportunity loss to them by way of royalty. That being so, the KPTs stand is that FCC
shall be settled between the parties and the TAMP has no role is fixing such charges.
The KPT
justifies its demand for FCC on the following grounds:
(a). The quantity of POL handled through VK pipeline is a
direct loss of traffic to the KPT.
(b). The KPTs investments on four oil jetties and other
related infrastructure will be under-utilised on commissioning of the VK pipelines.
(c). If cargo related charges and vessel-related charges on POL
products are taken together, the average revenue will be Rs.68/- per tonne. However, they are demanding a compensation for
loss of revenue on account of wharfage along, which is at present Rs.35/- PMT.
(vi). As clarified by the KPT, the
FCC is a royalty payment and has no nexus with the services rendered by the KPT or for use
of properties of the KPT.
(vii). The facility compensation charge
(FCC) is being raised in this case in the nature of a royalty with reference
to the opportunity cost of the traffic that will be diverted because of this
pipeline. It can be argued, as indeed has been contended by the PVKL, that way leave
charge for a pipeline does not depend, anywhere in the world, upon the quantity of
throughput passing through it. But, as has
been stressed by the KPT, the extraordinary circumstances governing this case deserve to
be singled out for specific recognition. In
on other pipeline case, possibly, there is such a definite diversion of assured (almost
dedicated) traffic. It is
noteworthy that, as has been contended by the KPT, all traffic generated from the two
refineries at Vadinar has in any case to pass through the KPT. That being so, the KPT contends, asking it to give
the way leave permission without any compensation will be like asking it to
commit hara-kiri!
The PVKL is of
course not obliged to accept such a proposition if it does not want to. It could have chosen a different route for its
pipeline without involving the KPT. For
whatever reason, this option was not exercised. The
PVKL was asked to proceed with execution of the Project even before these fundamental
financial issues were settled. It will be
relevant here to recognise the fact that the intention of the KPT to levy a FCC was known
to the PVKL before commencement of the pipeline-laying.
It may be possible for the PVKL to shift the burden or responsibility for
this development either to the OCC or (Even) to the Government. But, that will be of little avail in respect of
the dispute relating to the FCC. Having
forced a fait accompli on the KPT, the PVKL cannot, at this stage, argue only as a carrier
or a pipeline manager.
If the royalty
is being claimed to compensate for loss of an opportunity cost, it
can be argued that the KPT ought properly to raise this with the real beneficiary and not
with the carrier. The beneficiary
in this case can be either the refineries in Vaninar or, better still, the IOC in Kandla. But, once the pipeline is laid and commissioned,
the KPT will have no hold over either the refineries, or the PVKL, or the IOC in respect
of movement of the cargo. It is for this
reason that, as was explained at the joint hearing, the KPT has stopped construction of
the last stretch of the pipeline. Given the
extraordinary circumstances of this case, it may not be reasonable to expect the KPT at
this stage to start negotiating with the refineries or the IOC. Even if they did, in the event of a negative
response from both, what option can the KPT have? In
fairness to the KPT, it has to be appreciated that the complication (and, the anomalous
position) in this case has been caused by the execution of the Project in anticipation of
agreements of the details. It may be idle to
fix responsibility for what has happened. In
any case, it may not be within the purview of this Authority to go into such issues. The only relevant issue may be to consider
whether the KPT will be put to any (avoidable) loss by the project.
Viewed in this
perspective, the balance of convenience will be seen to lie in favour of the KPT to demand
a royalty by way of compensation for an opportunity cost.
(viii). The question to be settled is whether
the Authority will look into the matters relating to royalty and upfront payment in a BOT
/ BOOT contract. In the cases of
privatisation of port facilities, the payments made by the private operator towards
royalty and upfront payment form a part in the cost of rendering services at the private
terminal and will have implications on tariffs. The
Authority cannot remain as a mute spectator in such cases and take such costs as granted
in the tariff. The Authority must go into the
royalty and upfront payments before a concession is awarded.
(ix). In the present case,
however, PVKL is not a provider of port facility. The
FCC, if admissible and paid by the PVKL, will have implications in its cost structure for
rendering its service. However, this
Authority cannot go into the rates to be charged by the PVKL to its users. On this reckoning, this Authority will not like to
examine the merit and quantum of the FCC. The
issue regarding the FCC may be mutually settled between the PVKL and the KPT.
(x). During the joint
hearing, the PVKL pointed out that the KPTs comments on its representation covered
only three of the issues raised by it and argued that it would accordingly presume KPTs
acceptance of the other issues raised by it in the representation. A perusal of the PVKLs representation and
the KPTs comments thereon clearly shows that the KPTs letter to the TAMP is
specifically focused on three main issues raised by the PVKL seeking the intervention of
this Authority. The other issues made by the
PVKL about viability of the project, alternate route of the pipeline and its financial
implications, etc., are not relevant to the KPT and hence not commented upon by it. That being so, this argument of the PVKL cannot be
of any consequence to these proceedings.
10.
With reference
to the analysis given above, and based on a collective application of mind, the Authority
hereby decides as follows:
(i). There is no need
to frame a separate Scale of Rates for Way Leave Charges.
The existing rate and conditions for lease of KPT lands shall apply for the
lands allotted to the PVKL to lay underground pipelines in the land limits of the KPT.
(ii). The Authority cannot
interfere in the matter of levy of Facility Compensation Charge, which is a royalty
payment. This issue may be mutually settled
between the KPT and the PVKL.
S.Sathyam, Chairman